Thursday, July 1, 2010

Days 12-Today: Cabinets, Granite, Plumer

Thursday of last week the cabinet guys came in and installed the bottom and some of the top cabinets. They will be back today or tomorrow to install the rest of the upper cabinets, and to install the backordered oven cabinet.

The Granite Guy came in on Friday to measure and make a template for the Granite. On Wednesday the Granite Guy came to install the granite and it looks KOOL!

The Plumer came last night to prepare the pipes under the sink.and today he is coming back to fix the bathroom sink and install the Kitchen Sink.

When we first started this project, I was very happy with our contractor.  But in the last few days he has not shown up to fix the problem with one area of the ceiling. We have called him and left several messages, so far, no show.

Before the cabinets and the granite, after the flooring

base cabinets going in

Our cabinet guys

Most of the cabinets are in

Most of the cabinets are in


Most of the cabinets are in


The Granite:
 
 
Matty - The Granite Guy's dog

 
The Granite being installed

Finished, after granite and cabinets